About the Project

ADDRESS Parkside Crescent, Campbelltown

VALUE $13 Million ($200,000 Demolition)

OVERVIEW

The Campbelltown Hospital Multistorey Carpark Redevelopment involved the demolition of an existing maintenance building and warehouse.

Hazardous materials including asbestos and lead paint were identified within the structure and as demotion progressed, unidentified finds were discovered. All Hazardous materials were identified, isolated and removed as per industry standards and best practice.

The warehouse structure was dismantled, relocated and erected elsewhere for reuse. Once clearance certificate was obtained and warehouse relocated, soft strip out of internal non structural elements was completed, followed by demolition of main structure and in ground elements.

During the works, in the adjoining works zone, AW Edwards were completing works for stage 1 of the carpark build. In conjunction the hospital staff and public required intermittent access through the project to enable hospital operations to continue unhindered. This required constant co-ordination and communication with AW Edwards and Health Infrastructure, to ensure the works did not negatively effect stakeholders.